基于BIM的变电站数字化建设管控平台构建及应用

周圣栋1, 解蕾1, 宋若晨1, 陈浩2   

  1. 1. 国网上海市电力公司市区供电公司, 上海 200080;
    2. 国家电网有限公司华东分部, 上海 200120
  • 收稿日期:2018-09-14 修回日期:2018-12-25 出版日期:2019-05-05 发布日期:2019-05-14
  • 作者简介:周圣栋(1982-),男,工程师,从事电力系统及其自动化研究,E-mail:147398802@qq.com;解蕾(1983-),女,高级工程师,从事电力系统及其自动化研究,E-mail:sherry_jordan54@hotmail.com;宋若晨(1986-),男,高级工程师,从事电网规划研究,E-mail:song_yanshu@hotmail.com;陈浩(1984-),男,高级工程师,从事电网运行研究,E-mail:chenhao@ec.sgcc.com.cn

Building and Application of Substation Digital Construction Management Platform based on BIM

ZHOU Shengdong1, XIE Lei1, SONG Ruochen1, CHEN Hao2   

  1. 1. State Grid Shanghai Municipal Electric Power Compamy Urban Power Supply Company, Shanghai 200080, China;
    2. East China Branch, State Grid Corporation of China, Shanghai 200120, China
  • Received:2018-09-14 Revised:2018-12-25 Online:2019-05-05 Published:2019-05-14

摘要: 通过应用互联网、大数据、物联网等与建设进程相结合的办法,建立了整个变电站精细真实的数字信息模型。按施工管控步骤分解,实现模型按照工程甘特图进度建造增长。建立二维码扫码与模型的对应机制,落实数字化模型与建造过程中各真实节点的关联。同时,通过搭建相应的管控平台和开发App功能模块,实现对电网输变电项目的全寿命周期管理。采用BIM技术对项目工程量进行精确计算,加强物料成本信息的管控,提高工程量计算效率,节约了成本。

关键词: 变电站, 数字化信息技术, 模型, 管控, 工程量, 造价分析

Abstract: Through combination of the Internet, big data, Internet of things and the construction process, a deep and real digital information model of the substation is built. Based on the staged construction management process, the digital model can be implemented to display the construction growth according to the Gantt chart schedule. The QR code scan mechanism of the model is established to associate the digital model and the real construction nodes. At the same time, through building appropriate management platform and developing APP function module, the life cycle management of power transmission and transformation projects is achieved. The BIM technology is used to precisely calculate the project quantity, which strengthens the information control of material costs to improve the cost calculation efficiency and save costs.

Key words: substation, digital information technology, model, management, project quantity, cost analysis