超低排放改造工程脱硝催化剂的设计和采购分析

晏敏1, 李超2, 朱跃1   

  1. 1. 华电电力科学研究院,浙江 杭州 310030;
    2. 华电国际电力股份有限公司山东分公司,山东 济南 250014
  • 收稿日期:2016-09-22 出版日期:2017-09-25 发布日期:2017-09-11
  • 作者简介:晏敏(1982—),女,江西上高人,硕士,工程师,从事火电厂烟气脱硫脱硝研究。E-mail: yanmin0606@163.com
  • 基金资助:
    中国华电集团公司科技项目(火电厂烟气SCR脱硝催化剂评价与再生技术研究)(CHDKJ15-02-08)

Analysis on Design and Procurement of the Catalyst for Ultra Low Emission Reconstruction Project

YAN Min1, LI Chao2, ZHU Yue1   

  1. 1. China Huadian Electric Research Institute, Hangzhou 310030, China;
    2. Huadian Power International Corp Shandong Branch, Jinan 250014, China
  • Received:2016-09-22 Online:2017-09-25 Published:2017-09-11
  • Supported by:
    This work is supported by Science and Technology Program of China Huadian Corporation (Study on Evaluation and Regeneration Technology of Flue Gas SCR Denitration Catalyst in Thermal Power Plant) (No.CHDKJ15-02-08)

摘要: 随着氮氧化物排放限制的进一步严格,国内燃煤机组将开展有关超低排放的改造。在分析和总结前期SCR脱硝催化剂质量和运行特点的基础上,为规范和严格催化剂的设计和采购,结合当前脱硝催化剂的生产现状和脱硝系统运行控制现状,以及笔者对近3年脱硝催化剂的检测结果,对国内现役燃煤电厂SCR脱硝装置超低排放改造所涉及的脱硝催化剂的设计和采购,提出了具体注意事项,其中特别对加装备用层催化剂设计以及催化剂采购技术协议内容及其可能存在的问题进行了分析。

关键词: 燃煤电厂, 超低排放, 脱硝催化剂, 催化剂设计, 催化剂采购

Abstract: Along with the nitrogen oxide emission restrictions getting more stringent, ultra low emission retrofit will be carried out throughout all domestic coal-fired power plants. Based on the analysis and summary of the quality and operation characteristics of the in-service denitrification catalyst, in order to standardize and enforce the procedures in the catalyst design and procurement, by taking account of the current production status of denitration catalyst, the operation of denitration equipments as well as the test results of denitration catalyst in the recent 3 years, this article presents detailed issues for specific attentions in the design and procurement of the catalyst for the ultra low emission reconstruction in the SCR denitration device of current domestic coal-fired power plants. Especially, the possible problems are analyzed in the design and purchasing technical agreement for extra layer catalyst.

Key words: coal-fired power plant, ultra low emission, denitration catalyst, catalyst design, catalyst procurement