Type Selection and Layout Plan of 1 000 kV Substation Electrical Equipment in Cold and High Altitude Areas

WEN Weibing1, KANG Peng2, LIU Fei2, HU Junhui1, GUAN Lan1, ZHANG Fei2, YING Jie2   

  1. 1. State Grid Economic and Technological Research Institute Co., Ltd., Beijing 102209, China;
    2. Northwest Electric Power Design Institute Co., Ltd. of China Power Engineering Consulting Group, Xi'an 710075, China
  • Received:2017-10-30 Revised:2018-06-14 Online:2018-11-05 Published:2018-11-16
  • Supported by:
    This work is supported by the Science and Technology Project of SGCC (Research on Design Optimization of UHV AC Transmission and Transformation Engineering, No.B3440916K001).

Abstract: High altitude and low temperature will have a significant impact on type selection and layout of 1 000 kV substation equipment. At present, there are no design and construction experiences as well as related technical reserves for UHV substations under such ambient conditions. Based on an investigation of the current equipment manufacturing level and the operation conditions of existing projects in such environment, and after a comparison of different technical schemes, the paper proposes the external insulation correction method for 1 000 kV equipment, the type of 1 000 kV equipment bushing and the installing principle of heating belt for GIS under the ambient temperature of –45℃ and below the altitude of 3 500 m. The recommended equipment layout scheme is presented through technical and economic comparison. The research results can provide a reference for construction of the follow-up 1 000 kV substations.

Key words: UHV AC, 1 000 kV, substation, electrical equipment, selection, layout, high altitude, low temperature

CLC Number: