中国电力 ›› 2017, Vol. 50 ›› Issue (11): 59-64.DOI: 10.11930/j.issn.1004-9649.201702057

• 技术标准创新与实践专栏 • 上一篇    下一篇

架空输电线路铁塔组立施工技术标准体系优化研究与建议

张福轩1, 万建成2, 程更生3, 彭飞2, 江明2, 刘晨2   

  1. 1. 国家电网公司, 北京 100031;
    2. 中国电力科学研究院, 北京 100055;
    3. 国家电网公司直流建设分公司,北京 100052
  • 收稿日期:2017-02-16 出版日期:2017-11-25 发布日期:2017-11-29
  • 作者简介:张福轩(1963—),男,山西原平人,硕士,高级工程师,从事电网工程建设管理工作。E-mail: fuxuan_zhang@sgcc.com.cn
  • 基金资助:
    国家电网公司科技项目(GC71-17-007)

Optimization Research on Technical Standard System for Assembly and Erection Construction of the Steel Towers of Overhead Transmission Line

ZHANG Fuxuan1, WAN Jiancheng2, CHENG Gengsheng3, PENG Fei2, JIANG Ming2, LIU Chen2   

  1. 1. State Grid Corporation of China, Beijing 100031, China;
    2. China Electric Power Research Institute, Beijing 100055, China;
    3. State Grid DC Construction Company, Beijing 100052, China
  • Received:2017-02-16 Online:2017-11-25 Published:2017-11-29
  • Supported by:
    This work is supported by Science and Technology Project of State Grid Corporation of China(No. GC71-17-007).

摘要: 随着中国特高压电网的建设发展和铁塔组立施工工艺及配套施工装备技术水平的进步,以标准《750 kV架空送电线路铁塔组立施工工艺导则》(Q/GDW 112—2004)为核心逐步形成的整个架空输电线路铁塔组立施工技术标准体系存在部分内容重复、衔接性差以及在实际工作中适用性差等问题。因此需要系统梳理架空输电线路铁塔组立施工技术标准体系构成及存在问题,结合现有铁塔塔型特点、组立施工工艺特点和铁塔组立施工装备能力,提出进一步优化中国电力行业架空输电线路铁塔组立施工技术标准体系的框架结构,为铁塔组立施工提供技术支撑。

关键词: 输电线路, 铁塔组立, 标准体系, 框架结构

Abstract: With the rapid construction of UHV grid and the progress of construction technology and equipment of power transmission towers, some problems appear in the current technical standard system for assembly and erection construction of steel towers of overhead transmission line with the standard “Construction technology guidance for the assembling and erection of the steel towers of 750 kV overhead transmission line”(Q/GDW 112—2004)as the core, which include contents repetition, poor connection and poor applicability to the practical engineering. Therefore, in order to provide a technical support for assembling and erecting steel towers, it is necessary to further optimize the framework structure of existing China's electric power industry technical standard system for assembly and erection construction of steel towers of overhead transmission line, which should be carried out based on an analysis of the constitutions and problems of current standard system, and with a consideration of the features of tower types, the tower construction technology and the equipment for erecting steel tower.

Key words: overhead transmission line, steel tower assembly and erection, standard system, framework structure