Research and Application of Flow Path Retrofit Upgrade of the Subcritical 600 MW Turbine in Ninghai Power Plant

ZHANG Lei1, ZHANG Junjie1, FENG Liguo2, QIAO Jiafei1, XU Yatao1   

  1. 1. Shenhua Guohua(Beijing) Electric Power Research Institute Co. Ltd., Beijing 100025, China;
    2. Shenhua Zhejiang Guohua Zheneng Group Power Plant Co., Ltd., Ningbo 315612, China
  • Received:2016-12-28 Revised:2017-12-11 Online:2018-04-05 Published:2018-04-12
  • Supported by:
    This work is supported by Guohua Electric Power Science Project (Research and Application of Flow Path Retrofit Solution of Subcritical 600 MW Turbine of Guohua Company).

Abstract: In this paper, the research and application of flow path retrofit upgrade of the subcritical 600MW turbine in Ninghai Power Plant are introduced. Firstly, the performance and the existing problems of the subcritical 600 MW unit are analyzed, and the output status of the turbine before the upgrade is determined. Secondly, the achievements of the 300 MW steam turbine flow path retrofit upgrade projects in China and the guaranteed performance data from the manufacturers are studied; the thermal checking caluclation is conducted to get the expected performance index of the subcritical 600 MW steam turbine after the upgrade. Finally, the optimized design schemes, such as the cold end optimization and the final stage blade selection, are proposed after considering the upgrade schemes provided by the manufacturer to determinethe final scheme. With the flow path retrofit, the specific heat consumptionof the steam turbine is reduced by 332 kJ/(kW·h), and the economic benefit is remarkable.

Key words: 600 MW, steam turbine, flow path retrofit, heat rate, exhaust stage blade