中国电力 ›› 2018, Vol. 51 ›› Issue (4): 15-21,66.DOI: 10.11930/j.issn.1004-9649.201701044

• 电网 • 上一篇    下一篇

特高压输电线路污闪和风偏风险实时评估与预警

赵淳1,2, 宋暾昉3, 彭波4, 吴大伟2, 陶汉涛2, 邓永清5   

  1. 1. 南瑞集团有限公司(国网电力科学研究院有限公司), 江苏 南京 211106;
    2. 国网电力科学研究院 武汉南瑞有限责任公司, 湖北 武汉 430074;
    3. 国网四川省电力公司, 四川 成都 610041;
    4. 国家电网有限公司, 北京 100031;
    5. 武汉大学 电气工程学院, 湖北 武汉 430072
  • 收稿日期:2017-01-27 修回日期:2017-12-05 出版日期:2018-04-05 发布日期:2018-04-12
  • 作者简介:赵淳(1985-),男,湖北宜昌人,博士,高级工程师,从事电网雷电监测与防护技术研究,E-mail:zhao-chun@sgepri.sgcc.com.cn。
  • 基金资助:
    国家电网公司科技资助项目(524625150012)。

Real Time Assessment and Early Warning of Pollution Flashover and Wind Deflection Risk of UHV Transmission Lines Based on Meteorological Factors

ZHAO Chun1,2, SONG Tunfang3, PENG Bo4, WU Dawei2, TAO Hantao2, DENG Yongqing5   

  1. 1. NARI Group Corporation(State Grid Electric Power Research Institute), Nanjing 211106, China;
    2. Wuhan NARI Co., Ltd., State Grid Electric Power Research Institute, Wuhan 430074, China;
    3. State Grid Sichuan Electric Power Company, Chengdu 610041, China;
    4. State Grid Corporation of China, Beijing 100031, China;
    5. School of Electrical Engineering, Wuhan University, Wuhan 430072, China
  • Received:2017-01-27 Revised:2017-12-05 Online:2018-04-05 Published:2018-04-12
  • Supported by:
    This work is supported by Science and Technology Project of State Grid Corporation of China (No.524625150012).

摘要: 特高压输电线路跨越距离长,易受不同气象条件的影响,实现特高压输电线路在不同气象条件下的电气可靠性实时评估与预警对保障电力系统稳定可靠运行具有重要意义。分析了输电线路污闪和风偏闪络的机理,将气象数据引入特高压输电线路电气可靠性实时评估与预警中,结合未来1~72h数值天气预报的结果,建立了基于气象参数的特高压输电线路污闪、风偏风险实时评估与预警模型,预测特高压输电线路在不同气象条件下的污闪和风偏闪络电压,进而得到特高压输电线路在不同气象条件下的污闪和风偏闪络的风险等级,实现评估与预警。

关键词: 特高压输电线路, 实时评估与预警, 气象参数, 污闪, 风偏

Abstract: Due to the fact that UHV transmission lines have long distance and can be easily influenced by different meteorological conditions, it is of great significance to have a real-time assessment and early warning of the electrical reliability of UHV transmission lines under different meteorological conditions in order to ensure the stable and reliable operation of power system.This paper analyzes the mechanism of transmission line pollution flashover and wind deflection flashover, and introduces the meteorological parameters into real-time assessment and early warning of the electrical reliability of UHV transmission lines. With consideration of the numerical weather forcasting results for the next 1-72 hours, a real-time assessment and early warning model of UHV transmission line flashover and wind deflection risks is established based on meteorological parameters, which can predict the pollution flashover and wind deflection flashover voltage of transmission lines under different meteorological conditions and give early warnings based on their risk levels, realize the risk assessment and warning.

Key words: UHV transmission line, real-time assessment and early warning, meteorological parameters, pollution flashover, wind deflection

中图分类号: