中国电力 ›› 2017, Vol. 50 ›› Issue (3): 174-179.DOI: 10.11930/j.issn.1004-9649.2017.03.174.06

• 技术经济 • 上一篇    下一篇

基于河南省视角的新形势下分区域电力综合资源战略规划布局研究

白宏坤1, 王江波1, 尹硕1, 郑雅楠2, 刘永民1, 李虎军1   

  1. 1. 国网河南省电力公司经济技术研究院,河南 郑州 450052;
    2. 国家发展与改革委员会能源研究所,北京 100038
  • 收稿日期:2016-12-23 出版日期:2017-03-20 发布日期:2017-03-17
  • 作者简介:白宏坤(1971—),女,河南开封人,博士,高级工程师(教授级),从事能源经济、电力经济规划相关研究工作。E-mail:1420254015@qq.com

Research on Regional Electric Power Integrated Resource Strategic Planning under New Situation of Henan Province

BAI Hongkun1, WANG Jiangbo1, YIN Shuo1, ZHENG Yanan2, LIU Yongmin1, LI Hujun1   

  1. 1. State Grid Henan Economic and Technological Research Institute, Zhengzhou 450052, China;
    2. Energy Resarch Institute National Development and Reform Commission, Beijing 100038, China
  • Received:2016-12-23 Online:2017-03-20 Published:2017-03-17

摘要: 面对日益趋紧的资源环境约束,针对河南省地域、资源、需求特点,通过构建河南6大区域电网跨区输电线路的电力、电量约束,建立了考虑跨区输电的多区域河南省综合资源战略规划模型(HNIRSP),研究实现河南各地区资源的整体优化路径。河南省电力综合资源规划电力布局情景分析结果显示,除去EPP后,2014—2030年河南省需要新增装机需求总量为96 950 MW,与装机空间平衡结果相比,减少装机容量32 250 MW,可直接减少全社会投资约108.6亿元,减排CO2约11 627.0万t,减排SO2约37.7万t,减排NOx约32.8万t。

关键词: 综合资源战略规划, 电力布局, 需求侧管理, 能效电厂

Abstract: In the face of increasingly strained resources and environment, and against the geographic, resources and demand characteristics of Henan province, and through construction of power constraints of transregion grid transmission lines in six areas of Henan province, a Henan province integrated resource strategic planning model (HNIRSP) considering transregion power trasmission is established to study the regional resources overall optimization path of Henan province. The scenario analysis of HNIRSP shows that after removing the efficiency power plants(EPP), the needed installed capcacity of Henan province during 2014-2030 will reach 96 950 MW, deacreasing 32 250 MW compared with the balanced results, consequently reducing the whole social investment of 10.86 billion yuan, and reducing the emissions of CO2, SO2 and nitrogen oxides by 116.27 million tons, 377 000 tons and 328 000 tons, respectively.

Key words: integrated resource strategic planning, electricity power layout, demand side management, efficiency power plant

中图分类号: