中国电力 ›› 2021, Vol. 54 ›› Issue (4): 151-157.DOI: 10.11930/j.issn.1004-9649.202006014

• 区域综合能源系统规划与运行技术专栏 • 上一篇    下一篇

园区综合能源服务利益方运营关系和经营战略

徐文涛1, 李明轩2   

  1. 1. 国网宁夏电力有限公司, 宁夏 银川 750001;
    2. 清华大学 电机工程与应用电子技术系, 北京 100084
  • 收稿日期:2020-06-01 修回日期:2021-03-20 发布日期:2021-04-23
  • 作者简介:徐文涛(1982-),男,高级工程师,从事电力市场开拓、综合能源业务拓展研究,E-mail:ataox@126.com;李明轩(1987-),男,通信作者,博士研究生,从事虚拟电厂与辅助服务、综合能源技术研究,E-mail:limingxuan@tsinghua-eiri.org
  • 基金资助:
    国网宁夏电力有限公司科技项目 (5229YX20000U)

Operation Relationship and Business Strategy of Stakeholders of Park-Level Integrated Energy Services

XU Wentao1, LI Mingxuan2   

  1. 1. State Grid Ningxia Electric Power Co., Ltd., Yinchuan 750001, China;
    2. Department of Electrical Engineering, Tsinghua University, Beijing 100084, China
  • Received:2020-06-01 Revised:2021-03-20 Published:2021-04-23
  • Supported by:
    This work is supported by Science and Technology Project of State Grid Ningxia Electric Power Co., Ltd. (No.5229YX20000U).

摘要: 作为综合能源服务领域当前最具落地条件的领域,园区综合能源服务已受到工业、学术界越来越多的关注。园区综合能源服务相关利益方之间存在复杂的业务和利益耦合,亟须通过研究梳理利益方运营关系,指导园区综合能源服务的健康有序发展。通过分析园区综合能源服务的能量流、信息流与资金流,得出利益方运营关系。基于此,以电网企业为例,提出了开展园区综合能源服务发展的经营管理战略,即按照“以点带线、以点带面”的市场开拓思路,以示范项目为引领,拓展综合能源服务项目落地。

关键词: 综合能源服务, 利益方, 运营关系, 经营战略

Abstract: With the most applicable conditions in the field of integrated energy services (IES), the park-level IES has received more and more attention from industry and academia. Complex business and interest coupling exist among the stakeholders in the park-level IES, and it is urgent to study and sort out the operating relationships of the stakeholders to guide the healthy and orderly development of the park-level IES. The stakeholder operating relationship is obtained by analyzing of the energy flow, information flow, and capital flow of the park-level IES. By taking the grid enterprises as example, an operation strategy for the development of park-level IES is proposed. That is to expand the implementation of IES projects following the market development strategy of “proceeding from one location to a line or a region” and by taking the demonstration project as the guide.

Key words: integrated energy services, stakeholders, operating relationship, operation strategy